Regulator Orders Terra Nova FPSO Shutdown

December 20, 2019

Floating Production Intelligence LLC.
Terra_Nova_FPSO_100_100.jpg

The oil regulator for the Atlantic Canadian province of Newfoundland and Labrador has ordered a production shutdown by Suncor Energy's offshore Terra Nova site, finding the company was not compliant with required inspections and repairs.

Terra Nova, operating in the Atlantic Ocean 350 kilometers (217 miles) east of St. John's, failed to maintain and inspect critical safety equipment, carry out timely repairs and ensure it mitigated potential hazards, the Canada-Newfoundland and Labrador Offshore Petroleum Board (C-NLOPB) said in a statement on Thursday.

The regulator said Suncor, which operates the vessel, specifically failed to meet requirements regarding redundant fire water pump systems on the floating installation.

The suspension will continue until Suncor addresses the shortcomings, C-NLOPB said.

Terra Nova can store 960,000 barrels of oil, according to Suncor, which owns nearly 38%. Other companies, including Husky Energy, own smaller stakes in the project.

Suncor could not be immediately reached.


(Reporting by Rod Nickel in Winnipeg, Manitoba; Editing by Dan Grebler)

Floating Production Intelligence

  • Annual five year outlook and forecast FPSO database - The online database is updated every day – with information direct from primary sources. In the database are details for 200+planned projects, 390+ installations in service, 40+ floaters on order and 40+ floaters available. The database is fully searchable. Customized charts and spreadsheets can be directly produced from the database. Data are easily exported to excel spreadsheet.